Circular foundation concreting has been completed at unit 2’s evaporative cooling power of Novovoronezh II, a 16 November report of Atomenergoproekt, the power plant construction general contractor, says.

“In the nearest time, the construction workers will begin to install reinforced-concrete structures to form, together with the foundation, the concrete cooling tower’s base”, the company reports.

The cooling tower of Novovoronezh II’s unit 1 has already been erected to the design height of 171 m.


Source: Nuclear.Ru